Risk register

Also called risk log, risk registers

In short

A risk register is a structured record of an organisation's or project's identified risks, with their causes, consequences, owners, ratings, controls and planned actions.

  • Beginner
  • Document
  • Checked

In detail

A risk register turns risk management from conversation into a record that can be tracked. Each entry usually describes the risk clearly, often as an uncertain event with a cause and a consequence; names an owner responsible for managing it; rates its likelihood and impact before and after existing controls; lists the controls in place; records further actions with deadlines; and notes the date of the last review.

Registers exist at several levels. A project keeps its own register; departments keep operational registers; the board reviews a register of the most significant strategic and enterprise risks. Ratings are often combined into a score and shown on a heat map so that the most serious risks stand out, and risks above the organisation's appetite are escalated for decision.

A register is useful only if it is used. Common failings include vague descriptions, risks with no real owner, ratings that never change, long lists of trivial items and actions that are never followed up. Regular review in management meetings, clear escalation rules and links to key risk indicators keep the register a working tool rather than a compliance exercise.

Worked example

A project team rates a supplier delay at 4 for likelihood and 5 for impact on a 5-point scale. A second supplier is lined up, lowering the likelihood to 2.

  1. Score before the action: 4 × 5 = 20
  2. Score after the action: 2 × 5 = 10

The planned action halves the risk score from 20 to 10 on the team's scale.

In practice

Public bodies keep risk registers under HM Treasury's Orange Book principles, project methods require one for every project, and boards review the principal risks recorded in them.

Watch out

  • A register lists risks; it does not manage them. Actions and owners do.
  • Scores on different scales cannot be compared across registers.