Stockertim Dictionary · Risk management
Impact
Also called risk impact, severity, consequence rating
In short
The size of the consequence if a risk event happens, rated on a scale or measured in money, time, injuries or other units that matter to the organisation.
- Beginner
- Ratio or metric
- Checked
In detail
Impact is the second basic measure of a risk, alongside likelihood. It asks how bad, or how good, the outcome would be if the event happened. Organisations normally define an impact scale with several levels, such as minor, moderate, major and severe, and describe each level across the kinds of harm they care about: money lost, days of disruption, harm to people, regulatory action and damage to reputation.
Defining the levels in measurable terms is what makes ratings comparable. A small firm might call any loss above a set amount severe, while a large group sets a much higher threshold. When a risk has several consequences, many frameworks rate the impact at the level of the worst credible dimension, so that a modest financial loss with serious harm to customers is still rated highly.
Impact is easiest to estimate for losses that can be counted, such as repair costs. It is harder for slow or indirect harm, such as lost trust. Scenario workshops, past incidents in similar organisations and simple cost models all help to produce a defensible estimate rather than a guess.
Formula
Financial impact = direct loss + recovery cost + lost profit
- direct loss
- money or assets lost in the event
- recovery cost
- the cost of restoring normal operation
- lost profit
- profit forgone while disrupted
Worked example
A week-long warehouse outage would cause stock damage of 20,000, recovery costs of 15,000 and lost profit of 45,000.
- Financial impact: 20,000 + 15,000 + 45,000 = 80,000
The estimated impact is 80,000, which the retailer's scale rates as major.
In practice
A retailer estimates that a week-long warehouse outage would cost lost sales and extra freight, and compares the total with its impact scale to rate the risk.
Watch out
- Impact is rated as if the event happens; do not reduce it because the event is unlikely.
- Rate impact against the organisation's own scale; the same loss can be minor for one firm and severe for another.
Learn it properly
- Assessing risks: likelihood, impact and heat maps15 min lesson Free course: Enterprise risk management
- Costs and capacity: slippage, market impact and why paper results shrink15 min lesson Free course: Algorithmic trading
- Bias and fairness testing15 min lesson Free course: Human resources and AI
- Data protection impact assessments and privacy by design15 min lesson Free course: Human resources and data privacy
- Project risk and stakeholder management15 min lesson Free course: Project management
Official sources
- The Orange Book: management of risk, principles and concepts · HM Treasury
- SP 800-30 Rev. 1: Guide for conducting risk assessments · National Institute of Standards and Technology