Stockertim Dictionary · Consulting · Project management
Status report
Also called progress report, highlight report, RAG report
In short
A short regular update, often one page, covering progress against plan, risks and issues, decisions needed and the next steps.
- Beginner
- Document
- Checked
In detail
A status report tells the client and the team where an engagement stands. Most follow a fixed format so that changes are easy to spot: overall status, often shown red, amber or green; progress since the last report; activities planned for the next period; risks and issues with their owners; and decisions or support needed from the client. Some add the budget used, such as days spent against days agreed.
Regular reports build trust because problems are raised early, when they are cheap to fix. A late data request flagged in week two can be escalated; the same problem discovered at the final presentation cannot. Consistency matters more than length: one page every week beats a long document produced when things go wrong.
Status ratings are only useful if they are honest. Teams under pressure tend to report green until a problem becomes impossible to hide, a pattern sometimes called watermelon reporting, green outside and red inside. Clear criteria for each colour, and a culture that rewards raising bad news early, guard against it.
In practice
Every Friday the manager sends a one-page report: amber overall because two of five data items are late, three interviews completed, a decision needed on including the export business.
Watch out
- A green rating with a list of unresolved risks is not credible.
- A status report is not the place for new findings that have not been reviewed.
Learn it properly
Official sources
- Government Functional Standard GovS 002: Project delivery · UK Government
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.