Analysis plan
Also called work plan, hypothesis plan
In short
A table listing each hypothesis, what would have to be true for it to hold, the analysis and data that test it, its owner and its deadline.
- Intermediate
- Document
- Checked
In detail
An analysis plan turns an issue tree and its hypotheses into a schedule of work. Each row takes one hypothesis or question and states the evidence needed to settle it, the specific analysis to run, the data source, the person responsible and the date it is due. Many plans add a column for the expected output, often a sketch of the chart that would appear on the final page.
The plan makes priorities visible. Rows that would change the recommendation most, or that are quick to test, go first; rows that depend on slow data are started early so they do not hold up the end. It also shows gaps: a hypothesis with no feasible test needs a different approach, such as interviews or an external comparison.
Plans change as evidence comes in. Rejected hypotheses are struck through, new questions are added and resources move to the branches that matter. Reviewing the plan at each team meeting keeps effort focused and gives the manager an honest view of progress, which feeds the status report to the client.
In practice
A six-row plan for a cost review assigns one analyst to supplier spend by category, another to staffing ratios against comparable sites, and the manager to interviews, each with a dated output.
Watch out
- An analysis plan lists tests of hypotheses, not every analysis that could be done.
- If a row has no owner and date, it will not be done.