Risk response

Also called risk treatment, risk responses

In short

The planned action for a risk: avoiding, transferring, reducing or accepting a threat, or exploiting, sharing, enhancing or accepting an opportunity.

  • Intermediate
  • Process
  • Checked

In detail

A risk response is what the team decides to do about a risk once it has been assessed. For threats the usual options are to avoid it, by changing the plan so the risk cannot arise; to transfer it, for example through insurance or a fixed-price contract; to reduce it, by lowering its likelihood or impact; or to accept it, with or without a contingency. For opportunities the mirror options are to exploit, share, enhance or accept.

Each response should have an owner, a cost and a deadline, and it should be proportionate. Spending more on a response than the risk is worth is poor value, and the organisation's risk appetite sets the level at which residual risk is acceptable. Responses can create secondary risks, which also need recording.

Choosing a response is not the end. The owner carries out the action, the risk register is updated with the residual risk, and the risk is reviewed at each status meeting. Many risk failures in projects come not from missing risks but from responses that were agreed and never carried out.

In practice

Project risk registers record the chosen response and owner for each risk, and boards review whether responses are on track for the largest exposures.

Watch out

  • Transferring a risk moves its financial impact, but the project still suffers the delay.
  • Accepting a risk should be a decision, not the default for risks nobody owns.