Expected monetary value
Also called EMV, risk exposure value
In short
The probability of a risk multiplied by its financial impact, giving one figure that can be compared across risks or with a response's cost.
- Intermediate
- Ratio or metric
- Checked
In detail
Expected monetary value turns a risk into a number. A risk with a 25 per cent chance of costing 80,000 has an EMV of 20,000. Threats have negative values and opportunities positive ones, and adding the EMVs of all risks gives a rough measure of the project's overall exposure.
EMV helps with two decisions. It ranks risks so attention goes to the largest exposures first, and it tests responses: spending 5,000 to remove a risk with an EMV of 20,000 looks worthwhile, while spending 30,000 to do so does not. It also feeds decision trees, where the EMVs of different branches are compared to choose a course of action.
The figure is an average over many possible outcomes, not a prediction of what will happen. A single risk will either occur, costing the full impact, or not occur, costing nothing. For that reason EMV is useful for sizing reserves across many risks but is a weaker guide for one large, rare risk, where the full impact may be more important than the average.
Formula
EMV = probability × impact
- probability
- the chance the risk occurs, as a decimal
- impact
- the money gained or lost if it occurs
Worked example
A supplier failure has a 25% chance of costing 80,000. A backup contract would cost 6,000 and remove the risk.
- EMV of the risk: 0.25 × 80,000 = 20,000
- Net benefit of the backup: 20,000 - 6,000 = 14,000
On expected value, the backup contract is worth buying.
In practice
Risk registers often show probability, impact and EMV side by side, and contingency reserves are sized from the total EMV of the open threats.
Watch out
- Probabilities are usually judgements; EMV inherits their uncertainty.
- Averages hide catastrophic risks that an organisation could not survive even once.
Learn it properly
Official sources
- The Orange Book: management of risk · HM Treasury
- The Green Book: appraisal and evaluation in central government · HM Treasury
Facts last checked on 3 November 2026.