Management reserve
Also called unknown unknowns reserve, management contingency
In short
Money or time held outside the project baseline for risks nobody has identified, released only with the sponsor's approval.
- Intermediate
- Concept
- Checked
In detail
Management reserve covers the unknown unknowns: problems that were not on any risk register because nobody foresaw them. It is not part of the cost baseline the project manager controls. Instead it sits with the sponsor or the board, who decide whether a new, unforeseen issue justifies releasing money or time.
Together, the cost baseline and the management reserve make up the total project budget. Keeping them separate matters for performance measurement: earned value is measured against the baseline, so if reserve were mixed in, overspending would be hidden. When management reserve is released, the baseline is formally updated through change control.
The size of the reserve is usually a policy judgement based on the project's novelty and the organisation's history. First-of-a-kind projects need more than repeat work. A reserve that is never touched may have been too large and tied up capital that could have been used elsewhere, while one that runs out early is a sign the project was riskier than assumed.
Worked example
A project's cost baseline, including contingency, is 500,000. The organisation holds a 5% management reserve.
- Management reserve: 500,000 × 0.05 = 25,000
- Total project budget: 500,000 + 25,000 = 525,000
The project manager controls 500,000; the sponsor holds the remaining 25,000.
In practice
Approval routes for management reserve are set out in governance documents, often requiring a written case and a board decision before any release.
Watch out
- Using management reserve for known risks blurs accountability; that is what contingency is for.
- Releasing reserve should update the baseline, not quietly cover an overspend.
Learn it properly
Official sources
- NASA Cost Estimating Handbook · NASA
- Government Functional Standard GovS 002: Project Delivery · UK Government (Cabinet Office)
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.