Estimate at completion
Also called EAC, forecast at completion, FAC
In short
A forecast of a project's total cost by the time it finishes, often found by dividing the full budget by the cost performance index.
- Intermediate
- Ratio or metric
- Checked
In detail
The estimate at completion is the current best forecast of what the project will cost in total. It is compared with the budget at completion, the approved baseline, to show the expected overrun or underrun, known as the variance at completion.
There are several ways to calculate it, depending on what is assumed about the remaining work. If past cost efficiency is expected to continue, the budget at completion divided by the CPI is used. If the problems so far were one-off, the actual cost to date plus the remaining budget is used. A third method builds a fresh bottom-up estimate of the work left and adds it to the actual cost.
Comparing the different estimates is often more useful than any one. A wide gap between them points to uncertainty about future performance that the sponsor should understand before deciding whether to add funds, cut scope or stop the project.
Formula
EAC = BAC / CPI
- EAC
- the estimate at completion
- BAC
- the budget at completion, the approved total
- CPI
- the cost performance index to date
Worked example
A project has a budget at completion of 900,000. Its CPI to date is 0.9, and actual cost so far is 400,000 against earned value of 360,000.
- EAC if efficiency continues: 900,000 / 0.9 = 1,000,000
- EAC if the overrun was one-off: 400,000 + (900,000 - 360,000) = 940,000
- Expected overrun on the first method: 1,000,000 - 900,000 = 100,000
The forecast total lies between 940,000 and 1,000,000, against a budget of 900,000.
In practice
Boards receive the estimate at completion each month and decide whether management reserve, scope cuts or a revised business case are needed.
Watch out
- One formula is an assumption, not a fact; show the basis.
- An EAC that never moves while the CPI falls is a sign that forecasting has stopped.
Learn it properly
Official sources
- Earned value management · US Department of Energy, Office of Project Management
- NASA Cost Estimating Handbook · NASA
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.