Cost performance index

Also called cost efficiency index

In short

Earned value divided by actual cost: below 1 the project gets less than a unit of budgeted work for each unit spent.

  • Intermediate
  • Ratio or metric
  • Checked

In detail

The cost performance index measures cost efficiency. A CPI of 1 means the work done has cost exactly what was budgeted; 0.9 means each unit of money spent has bought only 0.9 of a unit of planned work, so the project is over budget; 1.1 means it is under budget for the work achieved.

CPI is valuable because it tends to be stable. Studies of large projects have found that once a project is a fifth or so complete, its cumulative CPI rarely improves much. That makes it a strong early warning: a CPI of 0.85 at the 20 per cent mark is a signal to act, not to wait for things to even out.

CPI feeds forecasts. Dividing the budget at completion by the CPI gives one estimate at completion, which assumes the rest of the work will be done at the same efficiency. Managers often compare this with other forecasts to test how realistic the current budget is.

Formula

CPI = EV / AC

CPI
the cost performance index
EV
earned value
AC
actual cost

Worked example

A project has earned 360,000 of value and spent 400,000.

  1. CPI: 360,000 / 400,000 = 0.9

The project is getting 0.9 of budgeted work for each unit spent, so it is running over budget.

In practice

Monthly reports show CPI alongside the schedule performance index, and many organisations set thresholds at which a project must explain itself to the board.

Watch out

  • CPI says nothing about schedule; a project can be on budget and very late.
  • A good CPI can hide deferred work that has not been charged yet.