Planned value
Also called budgeted cost of work scheduled, BCWS
In short
The budgeted cost of the work scheduled to be done by a given date, read from the project's time-phased cost baseline.
- Intermediate
- Ratio or metric
- Checked
In detail
Planned value answers the question: how much work, in budget terms, should we have done by now? It comes from the cost baseline, which spreads each work package's budget over the time it is scheduled to run. If by the end of month three the plan called for work worth 120,000 to be complete, the planned value at that point is 120,000.
On its own planned value says nothing about performance; it is the yardstick. Comparing it with earned value, the budgeted cost of the work actually completed, gives the schedule variance and the schedule performance index. At the end of the project, planned value equals the budget at completion.
Planned value is only meaningful if the baseline is sound and kept under change control. If the scope changes and the baseline is not updated, comparisons become misleading. That is why earned value systems are built on a stable work breakdown structure with a budget and schedule for every work package.
Formula
Schedule variance = EV - PV
- EV
- earned value to date
- PV
- planned value to date
Worked example
A project's baseline calls for 120,000 of work by the end of month three. Work actually completed is budgeted at 105,000.
- Schedule variance: 105,000 - 120,000 = -15,000
- Schedule performance index: 105,000 / 120,000 = 0.875
The project has completed less work than planned: it is behind schedule.
In practice
Earned value reports plot planned value as an S-curve against earned value and actual cost, so trends are visible month by month.
Watch out
- Planned value is not money spent; that is actual cost.
- Schedule variance in money terms tends towards zero at the end even for a late project.
Learn it properly
Official sources
- Earned value management · US Department of Energy, Office of Project Management
- NASA Cost Estimating Handbook · NASA
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.