Actual cost

Also called AC, actual cost of work performed, ACWP

In short

The money actually spent on the work completed by a given date, taken from the project's cost records.

  • Intermediate
  • Ratio or metric
  • Checked

In detail

Actual cost is the real spending on a project's work up to a point in time, including labour, materials, equipment and subcontracts charged to the project. In earned value management it is compared with earned value to see whether the work done has cost more or less than budgeted.

Getting actual cost right needs good cost collection. Time sheets must be booked to the right work packages, invoices must be matched to the period in which work was done, and accruals made for work completed but not yet billed. Otherwise actual cost lags behind progress and the project looks cheaper than it is, only to swing over budget later.

Actual cost is also the base for forecasts. The estimate at completion adds the actual cost so far to the estimated cost of the remaining work. Comparing the estimate with the budget at completion tells the sponsor whether more money will be needed.

Formula

CPI = EV / AC

CPI
the cost performance index
EV
earned value to date
AC
actual cost to date

Worked example

By month four a project has earned 200,000 of value and spent 250,000.

  1. Cost variance: 200,000 - 250,000 = -50,000
  2. Cost performance index: 200,000 / 250,000 = 0.8

Each unit spent is producing 0.8 of a unit of budgeted work.

In practice

Finance and project teams reconcile actual cost each month so earned value reports use the same figures as the accounts.

Watch out

  • Late invoices make actual cost look low; accrue for work done.
  • Spending below plan is not good news if the work is also behind.

Learn it properly

Official sources

Facts last checked on 3 November 2026.

Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.