Contingency reserve
Also called contingency, risk contingency, known unknowns reserve
In short
Money or time held inside the project baseline for identified risks that may occur, usually controlled by the project manager.
- Intermediate
- Concept
- Checked
In detail
A contingency reserve covers risks the team has identified but cannot be sure will happen, the so-called known unknowns. If the risk register shows a 30 per cent chance of a supplier delay costing 50,000, a share of that exposure is set aside in the budget. If the delay happens, the reserve pays for it without a change to the baseline; if it does not, the money may be released.
The size of the reserve should come from analysis rather than a flat percentage. Expected monetary values of the main risks, or a cost risk simulation, give a defensible figure, and the reserve is tied to specific risks so its use can be tracked. Public sector guidance also asks estimators to adjust for optimism bias, the tendency of early estimates to understate cost and time.
Contingency sits inside the cost baseline and is visible, which separates it from padding hidden in individual estimates. It is different from management reserve, which is held outside the baseline for risks nobody has identified and needs a higher level of approval to release.
Worked example
Two identified risks: a 40% chance of a 30,000 delay cost and a 20% chance of a 50,000 redesign.
- Expected value of risk 1: 0.40 × 30,000 = 12,000
- Expected value of risk 2: 0.20 × 50,000 = 10,000
- Contingency reserve: 12,000 + 10,000 = 22,000
A contingency of 22,000 covers the expected cost of the known risks.
In practice
Project reports show the contingency remaining against the risks still open, so a board can see whether reserves are being consumed faster than risks are retired.
Watch out
- Contingency is not spare money for new scope.
- A reserve sized on expected value will not cover every risk if several occur at once.
Learn it properly
- Estimating and cost management15 min lesson Free course: Project management
- Production budgets and schedules5 min lesson Free course: Media production
- Risk-based internal audit planning15 min lesson Free course: Internal audit and internal control
- Event planning: objectives, audience, format and budget5 min lesson Free course: Sponsorship, events and experiential marketing
- Notes to the accounts: leases, provisions, contingencies and share-based pay15 min lesson Free course: Reading annual reports and prospectuses
Official sources
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.