Work breakdown structure
Also called WBS
In short
A hierarchy that breaks all the work of a project into smaller pieces, ending in work packages that can be estimated, assigned and tracked.
- Intermediate
- Concept
- Checked
In detail
A work breakdown structure starts with the whole project at the top and divides it level by level into deliverables and sub-deliverables until the pieces are small enough to plan. The lowest level holds work packages, each of which one person or team can own, estimate and report on. A house build might split into foundations, structure, roof, services and finishes, and services into plumbing, electrics and heating.
The WBS follows the 100 per cent rule: the lower levels together must contain all the work of the level above, and nothing outside the scope. That makes it a check on completeness. If a deliverable is missing from the WBS, nobody has planned, costed or assigned it.
Many other plans hang from the WBS. Activities for the schedule are derived from work packages, bottom-up estimates add their costs, and earned value is measured against them. Each element usually gets a code and a short description in a WBS dictionary so that the whole team uses the same language.
Worked example
A training project has three deliverables. Course design is estimated at 12,000, delivery at 20,000 and evaluation at 4,000.
- Total of the work packages: 12,000 + 20,000 + 4,000 = 36,000
Under the 100 per cent rule, the project budget at that level is 36,000 plus any reserves.
In practice
Project teams draft the WBS in a workshop with the people who will do the work, then use it to build the schedule, the cost estimate and the responsibility chart.
Watch out
- A WBS is organised by deliverables, not by the order work happens; the schedule handles sequence.
- Breaking work down too far creates admin without adding control.
Learn it properly
Official sources
- Government Functional Standard GovS 002: Project Delivery · UK Government (Cabinet Office)
- NASA Cost Estimating Handbook · NASA
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.