Total float
Also called float, total slack, slack
In short
The time an activity can be delayed without delaying the end of the project, found as its latest start minus its earliest start.
- Intermediate
- Ratio or metric
- Checked
In detail
Total float measures schedule flexibility. An activity that could start on day 10 at the earliest but need not start until day 15 without moving the finish date has five days of total float. Activities on the critical path have zero float, which is why any slip there moves the whole project.
Float is calculated from the network. The forward pass gives each activity's earliest start and finish; the backward pass gives its latest start and finish. Total float is the gap between latest and earliest, and the same answer comes from either the start dates or the finish dates.
Float belongs to a path, not to one activity alone. If an early activity uses up its float, later activities on the same path lose theirs, and the path may become critical. Planners therefore watch float shrink over time as a warning sign, and many organisations agree in advance who may use float and when.
Formula
Total float = latest start - earliest start
- latest start
- the last day the activity can start without delaying the project
- earliest start
- the first day the activity can start once its predecessors finish
Worked example
An installation task has an earliest start of day 8 and a latest start of day 13.
- Total float: 13 - 8 = 5 days
The task can slip up to 5 days without moving the project end date.
In practice
Schedule health checks report how many activities have negative, zero or very low float, because a schedule with float almost everywhere near zero is fragile.
Watch out
- Free float, the delay possible without affecting the next activity, is smaller than or equal to total float.
- Negative float means the schedule already cannot meet a fixed date.
Learn it properly
- Scheduling, networks and the critical path15 min lesson Free course: Project management
- How insurers make money: premiums, claims and float15 min lesson Free course: Insurance and risk transfer
- Short squeezes: Volkswagen (2008) and GameStop (2021)15 min lesson Free course: Short selling
- Budgeting and budgetary control15 min lesson Free course: Management and cost accounting
- Reading a prospectus: use of proceeds, risk factors, lock-ups and dilution15 min lesson Free course: Reading annual reports and prospectuses
Official sources
- NASA Cost Estimating Handbook · NASA
- Government Functional Standard GovS 002: Project Delivery · UK Government (Cabinet Office)