Fast-tracking
Also called fast tracking, schedule fast-tracking
In short
Shortening a schedule by doing in parallel activities that were planned to run one after the other, which adds risk of rework.
- Intermediate
- Process
- Checked
In detail
Fast-tracking compresses a schedule by overlapping work. Instead of waiting for design to finish completely before construction begins, the team starts building the parts whose design is settled while the rest is still being drawn. The critical path gets shorter because two activities that were in sequence now partly run at the same time.
The cost of fast-tracking is risk rather than money. If the earlier activity changes after the later one has started, work already done may have to be redone. The method therefore suits dependencies that are discretionary, chosen as good practice rather than forced by physics or law, and work packages whose inputs are unlikely to change.
Managers usually compare fast-tracking with crashing. Crashing adds resources and cost with fairly predictable results; fast-tracking adds little direct cost but raises the chance of rework and confusion. Many recovery plans use both, fast-tracking where overlap is safe and crashing where money buys time cheaply.
Worked example
Design takes 20 days and build takes 30 days in sequence. The team agrees build can start once design is 75% complete.
- Original duration: 20 + 30 = 50 days
- Build starts after 0.75 × 20 = 15 days
- New duration: 15 + 30 = 45 days
Overlapping saves 5 days, at the risk of rework if late design changes affect what has been built.
In practice
Construction, product launches and system implementations often fast-track by starting procurement or training before design sign-off, with checkpoints to stop the overlap if designs change.
Watch out
- Mandatory dependencies, such as concrete curing before loading, cannot be fast-tracked.
- Fast-tracking on unstable requirements usually costs more time than it saves.
Learn it properly
Official sources
- NASA Cost Estimating Handbook · NASA
- Government Functional Standard GovS 002: Project Delivery · UK Government (Cabinet Office)
Facts last checked on 3 November 2026.