Stockertim Dictionary · Project management · Strategy and management
Rework rate
Also called rework, first-time-right rate, redo rate
In short
The share of items passing through a process that must be corrected or done again, usually expressed as a percentage.
- Beginner
- Ratio or metric
- Checked
In detail
Rework rate measures how often work is not right first time. If 200 invoices are processed in a week and 30 have to be corrected and reprocessed, the rework rate is 15 per cent. Each reworked item costs extra effort, adds to cycle time and often frustrates the customer who has to supply information again.
Rework is one of the classic forms of waste in lean thinking. Its causes are usually upstream of where it is found: unclear forms, missing information at the start, poor training, confusing systems or a hand-off that loses detail. Measuring rework at each step, and asking why each item needed correcting, points to the causes worth fixing.
The complement of the rework rate is the first-time-right rate. Improving it typically lowers cost and speeds up the process at the same time, because capacity freed from correcting errors can handle new work. Because of this, analysts often treat a high rework rate as a stronger signal than slow processing.
Formula
Rework rate = items reworked / items processed
- items reworked
- items that had to be corrected or redone
- items processed
- all items handled in the period
Worked example
A team processes 200 invoices in a week; 30 are sent back for correction. Each correction takes 20 minutes.
- Rework rate: 30 / 200 = 15%
- Time lost: 30 × 20 = 600 minutes
- In hours: 600 / 60 = 10 hours
Fifteen per cent of invoices cost the team ten extra hours a week.
In practice
Operations dashboards show rework and first-time-right rates by step and by cause, and improvement projects set targets for both.
Watch out
- Rework counted only at the end misses corrections made quietly along the way.
- Blaming the step that finds errors misses the step that creates them.
Learn it properly
Official sources
- Lean: Ohno's eight wastes · NHS England (Quality, Service Improvement and Redesign tools)
- Measurement for improvement: an overview · NHS England (Quality, Service Improvement and Redesign tools)
Facts last checked on 3 November 2026.