Cycle time
Also called process cycle time, end-to-end time, throughput time
In short
The elapsed time from the start of a process to its end for one item, including waiting time as well as working time.
- Beginner
- Ratio or metric
- Checked
In detail
Cycle time measures how long a single item, such as an application, an order or a repair, takes to pass through a process from the moment it starts to the moment it is finished. It counts calendar time, not just effort, so it includes every period the item spends in a queue, waiting for approval or sitting in someone's inbox.
The gap between cycle time and working time is often startling. A loan application might need only two hours of actual work but take ten days to complete, because it waits between each step. Process efficiency, the share of cycle time spent on work that adds value, is frequently below ten per cent in office processes, which is why removing waiting usually gives larger gains than speeding up the work itself.
Cycle time is a customer-facing measure, because customers experience the whole wait. Analysts measure it for many items, since averages hide variation, and report the spread as well as the typical value. After a change, cycle time is one of the simplest ways to show whether the to-be process works better than the as-is.
Formula
Process efficiency = working time / cycle time
- working time
- time spent actively working on the item
- cycle time
- total elapsed time from start to finish
Worked example
An application takes 10 working days of 8 hours from receipt to decision, and the steps themselves need 4 hours of work.
- Cycle time in hours: 10 × 8 = 80 hours
- Process efficiency: 4 / 80 = 5%
Ninety-five per cent of the cycle time is waiting, so queues are the main target.
In practice
Service teams track median and 90th percentile cycle times each week, and process redesigns set cycle time targets for the to-be process.
Watch out
- Different teams define start and end differently; agree the clock before comparing.
- An average cycle time hides the long tail of cases customers complain about.
Learn it properly
Official sources
- Flow: reduce unnecessary waits · NHS England (Quality, Service Improvement and Redesign tools)
- Value stream mapping · NHS England (Quality, Service Improvement and Redesign tools)
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.