Parallel run

Also called parallel running, parallel payroll, parallel test

In short

Processing the same pay period in the old and new systems from the same inputs and comparing every result until the differences are explained and within tolerance.

  • Advanced
  • Process
  • Checked

In detail

A parallel run is the main test of a new payroll system. The same period is processed in both systems from identical inputs, and the results are compared employee by employee: gross pay, each deduction, net pay, employer costs and the totals due to tax and pension bodies. Every difference is investigated and classified as a new-system error, an old-system error or an expected change.

Most payroll projects run at least two parallel periods, ideally including tricky events such as starters, leavers, backdated pay changes and year-end. The project sets acceptance criteria in advance, such as all differences explained and no unexplained difference above a small amount per person, and does not go live until they are met.

Parallel runs are expensive because the payroll team processes everything twice. Some projects reduce the burden by comparing a large sample instead of everyone, but for pay, where errors hit people's finances and legal duties, full comparison is common. After go-live, the old system is usually kept available for a period in case it is needed.

In practice

In the first parallel run, 30 of 1,200 employees show different net pay. Twenty-six differences trace to a pension rule set up wrongly in the new system, four to old-system errors, and the run is repeated.

Watch out

  • Matching totals can hide individual errors that cancel out; compare person by person.
  • An unexplained difference is a failed test, however small.