Labour efficiency variance

Also called labor efficiency variance, direct labour efficiency variance, labour usage variance

In short

The difference between the hours that should have been worked for the actual output and the hours actually worked, valued at the standard rate.

  • Intermediate
  • Ratio or metric
  • Checked

In detail

The labour efficiency variance shows whether staff produced the output in more or less time than the standard allows. It takes the standard hours for the actual output, subtracts the actual hours worked, and values the difference at the standard hourly rate. A separate labour rate variance captures differences in the rate actually paid.

A favourable efficiency variance can come from experienced staff, better tools, good materials or improved methods. An adverse variance can come from inexperienced or poorly trained staff, machine breakdowns, poor materials, bad scheduling or a standard that no longer fits the process. Where staff are paid for idle time, such as waiting for materials, that time is often reported as a separate idle time variance so it is not hidden in efficiency.

In many organisations labour is effectively a fixed cost in the short term, because staff are salaried. The efficiency variance then measures productivity rather than a saving that can be banked.

Formula

Labour efficiency variance = (Standard hours for actual output − Actual hours) × Standard rate

Standard hours for actual output
hours allowed for the output made
Actual hours
hours actually worked
Standard rate
the planned hourly wage rate

Worked example

Each unit should take 0.5 hours at a standard rate of 20 an hour. The team makes 1,800 units in 850 hours.

  1. Standard hours: 1,800 × 0.5 = 900
  2. Hours saved: 900 − 850 = 50
  3. Variance: 50 × 20 = 1,000

The labour efficiency variance is 1,000 favourable.

In practice

Contact centres and warehouses measure tasks against standard times and review efficiency with team leaders, alongside quality measures so that speed does not come at the cost of errors.

Watch out

  • Value the hours at the standard rate; the rate variance is separate.
  • Pushing for a favourable efficiency variance can damage quality and safety.