In short
The difference between the hours that should have been worked for the actual output and the hours actually worked, valued at the standard rate.
- Intermediate
- Ratio or metric
- Checked
In detail
The labour efficiency variance shows whether staff produced the output in more or less time than the standard allows. It takes the standard hours for the actual output, subtracts the actual hours worked, and values the difference at the standard hourly rate. A separate labour rate variance captures differences in the rate actually paid.
A favourable efficiency variance can come from experienced staff, better tools, good materials or improved methods. An adverse variance can come from inexperienced or poorly trained staff, machine breakdowns, poor materials, bad scheduling or a standard that no longer fits the process. Where staff are paid for idle time, such as waiting for materials, that time is often reported as a separate idle time variance so it is not hidden in efficiency.
In many organisations labour is effectively a fixed cost in the short term, because staff are salaried. The efficiency variance then measures productivity rather than a saving that can be banked.
Formula
Labour efficiency variance = (Standard hours for actual output − Actual hours) × Standard rate
- Standard hours for actual output
- hours allowed for the output made
- Actual hours
- hours actually worked
- Standard rate
- the planned hourly wage rate
Worked example
Each unit should take 0.5 hours at a standard rate of 20 an hour. The team makes 1,800 units in 850 hours.
- Standard hours: 1,800 × 0.5 = 900
- Hours saved: 900 − 850 = 50
- Variance: 50 × 20 = 1,000
The labour efficiency variance is 1,000 favourable.
In practice
Contact centres and warehouses measure tasks against standard times and review efficiency with team leaders, alongside quality measures so that speed does not come at the cost of errors.
Watch out
- Value the hours at the standard rate; the rate variance is separate.
- Pushing for a favourable efficiency variance can damage quality and safety.
Learn it properly
Official sources
- SFFAS 4: Managerial Cost Accounting Standards and Concepts · Federal Accounting Standards Advisory Board
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.