Skip to content

Stockertim Dictionary · Accounting · Business

Adverse variance

Also called adverse variances, unfavourable variance, unfavorable variance, negative variance

In short

A difference from budget that reduces profit, such as income below budget or costs above budget; also called an unfavourable variance.

  • Beginner
  • Concept
  • Checked

In detail

An adverse variance, marked A or written in brackets, is any departure from plan that leaves profit lower than budgeted. On a revenue line it arises when actual income falls short: fees of 45,000 against a plan of 48,000 are 3,000 adverse. On a cost line it arises when spending overshoots: agency staff costing 7,500 against 6,000 are 1,500 adverse, even though the actual figure is the larger one.

In standard costing, adverse variances are broken down further to find the cause. A material cost overspend can be split into a price variance, from paying more per kilogram, and a usage variance, from using more kilograms. Labour overspends split into rate and efficiency. Each part points to a different manager: purchasing for price, production for usage.

An adverse figure starts an inquiry rather than ending one. Many have ordinary explanations: higher volumes that also raised sales, a price rise across the whole market, a one-off repair, or an invoice from last month booked late. Others reveal real problems such as waste, poor buying or a weak sales pipeline. Some adverse variances are deliberate trade-offs, like paying overtime to finish an order that earns more than it costs.

Organisations usually set a level above which adverse variances must be explained, sometimes combining an amount and a percentage. Recurring adverse variances on the same line may show that the budget itself needs revising rather than the activity.

Formula

Income line: budget − actual; cost line: actual − budget; adverse when the result is positive

budget
the planned amount for the line and period
actual
the amount actually recorded

Worked example

A consultancy in Abuja compares its May results with budget: fee income of 48,000 was planned and 45,000 earned; agency staff of 6,000 was planned and 7,500 spent.

  1. Fee income: 48,000 − 45,000 = 3,000 adverse
  2. Agency staff: 7,500 − 6,000 = 1,500 adverse
  3. Total reduction in profit: 3,000 + 1,500 = 4,500

Profit is 4,500 below budget, from income falling short and a cost overrunning.

In practice

Monthly management packs list adverse variances above an agreed level with an owner and an explanation, and track whether the same lines recur so that persistent problems or unrealistic budgets come to light.

Watch out

  • An adverse cost variance can come with a larger favourable sales variance; read related lines together.
  • Timing differences, such as late invoices, create adverse variances that reverse the following month.