High-low method

Also called high low method, high-low technique

In short

A way of splitting a semi-variable cost into fixed and variable parts by comparing total costs at the highest and lowest levels of activity.

  • Intermediate
  • Process
  • Checked

In detail

The high-low method assumes that, within the normal range, a semi-variable cost moves in a straight line with activity. Take the period with the highest activity and the period with the lowest. The difference in cost between them must be caused by the difference in activity, because the fixed part is the same in both. Dividing the cost difference by the activity difference gives the variable cost per unit.

The fixed part is then found by taking total cost at either level and subtracting the variable cost for that level. The result is a simple cost formula, fixed cost plus variable cost per unit times activity, that can be used to forecast costs at other activity levels and to build flexible budgets.

The method is quick but crude. It relies on just two observations, which may be unusual months, and ignores the rest of the data. Regression analysis uses all the points and is more reliable when good data are available.

Formula

Variable cost per unit = (Cost at high activity − Cost at low activity) / (High activity − Low activity)

Cost at high activity
total cost in the busiest period
Cost at low activity
total cost in the quietest period
High activity
the highest volume observed
Low activity
the lowest volume observed

Worked example

A laundry's maintenance cost was 23,000 in its busiest month, at 8,000 machine hours, and 15,000 in its quietest, at 4,000 hours.

  1. Variable rate: (23,000 − 15,000) / (8,000 − 4,000) = 2
  2. Fixed part: 23,000 − 2 × 8,000 = 7,000
  3. Forecast at 6,000 hours: 7,000 + 2 × 6,000 = 19,000

Maintenance costs about 7,000 a month plus 2 a machine hour, so 19,000 at 6,000 hours.

In practice

Small businesses without statistical software use the high-low method to estimate how utility and maintenance costs will change as they grow.

Watch out

  • Use the highest and lowest activity levels, not the highest and lowest costs.
  • An unusual month at either end distorts the result; check that both are typical.