Portfolio Construction (8–12%)

Planning, behaviour and risk management: CFA Level I practice

The portfolio management process, the investment policy statement, behavioural biases and risk management.

Planning, behaviour and risk management: sample questions and answers

Original practice questions on this topic. Decide on your answer, then open it to check. Practice draws on 18 questions on this topic.

A pension fund's long-term policy mix is 60% equities and 40% bonds. Because its managers expect equities to do poorly over the next six months, they move temporarily to 50% equities and 50% bonds.

Question 1 What is this move best described as?

Choose one answer

  1. Strategic asset allocation
  2. Tactical asset allocation
  3. Rebalancing to the policy mix
Show the answer

Answer: Tactical asset allocation

Tactical asset allocation is a short-term, deliberate move away from the strategic (policy) mix to exploit expected market conditions, here 50/50 instead of 60/40. Rebalancing would move the portfolio back towards 60/40, and the strategic allocation is the long-term 60/40 policy itself.

Source: CFA Level I topic area: Portfolio Management (strategic and tactical asset allocation)

Question 2 Which investor typically has the longest time horizon?

Choose one answer

  1. A university endowment intended to exist in perpetuity
  2. A bank managing its deposit-funded securities portfolio
  3. A property and casualty insurer funding claims
Show the answer

Answer: A university endowment intended to exist in perpetuity

Endowments aim to support their institution indefinitely, so their horizon is very long and they can hold illiquid assets. Banks and non-life insurers have short-term liabilities and need liquidity.

Source: CFA Level I topic area: Portfolio Construction (types of investors)

A fund holds 50 million. Its daily returns are assumed normally distributed with a mean of zero and a standard deviation of 1.2%. The one-tailed z-value at 5% is 1.645.

Question 3 What is the fund's one-day 5% parametric VaR?

Choose one answer

  1. 600,000
  2. 987,000
  3. 1,398,000
Show the answer

Answer: 987,000

VaR = value x z x sigma = 50,000,000 x 1.645 x 1.2% = 987,000. 600,000 is one standard deviation; 1,398,000 uses z = 2.33, the 1% level.

Source: CFA Level I topic area: Portfolio Construction (value at risk)

Practise planning, behaviour and risk management

Ten questions at a time, from 18 questions on this topic, each explained as you go.

Practise this topic All topics

More topics

Practice questions. These are original practice questions written by Stockertim to help you prepare for CFA Level I. They are not real CFA exam questions or CFA Institute curriculum material. Stockertim is not affiliated with CFA Institute. For the real test, use the official website. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute. CFA Institute does not endorse, promote or warrant the accuracy or quality of Stockertim's practice questions.