Work package

Also called work packages

In short

The lowest level of a work breakdown structure: a defined piece of work that one person or team can own, estimate, schedule and report on.

  • Intermediate
  • Concept
  • Checked

In detail

A work package is where planning meets doing. It has a clear output, an owner, an estimate of effort and cost, a planned start and finish, and a way to tell when it is complete. Typical work packages are small enough to finish within a reporting period or two, so that progress can be measured honestly rather than guessed.

Each work package is broken into the activities that appear on the schedule. Its cost becomes part of the bottom-up estimate and the budget, and in earned value management it is a natural control point: the budget of a finished work package is earned value the project can claim.

Defining work packages well makes delegation easier. The owner knows what is expected, what resources they have and when to report. Vague packages such as "testing, as needed" make it impossible to know whether the project is on track, and they tend to grow quietly until the budget runs out.

In practice

Contracts with suppliers are often written around work packages, with a price and acceptance test for each, and project boards review progress package by package.

Watch out

  • A package with no single owner tends to have no progress either.
  • Packages that run for many months hide slippage until it is too late to recover.