Skip to content

아직 한국어로 제공되지 않습니다. 한국어로 제공되는 모든 내용 보기

Stockertim Dictionary · Project management

Work breakdown structure

Also called WBS

In short

A hierarchy that breaks all the work of a project into smaller pieces, ending in work packages that can be estimated, assigned and tracked.

  • Intermediate
  • Concept
  • Checked

In detail

A work breakdown structure starts with the whole project at the top and divides it level by level into deliverables and sub-deliverables until the pieces are small enough to plan. The lowest level holds work packages, each of which one person or team can own, estimate and report on. A house build might split into foundations, structure, roof, services and finishes, and services into plumbing, electrics and heating.

The WBS follows the 100 per cent rule: the lower levels together must contain all the work of the level above, and nothing outside the scope. That makes it a check on completeness. If a deliverable is missing from the WBS, nobody has planned, costed or assigned it.

Many other plans hang from the WBS. Activities for the schedule are derived from work packages, bottom-up estimates add their costs, and earned value is measured against them. Each element usually gets a code and a short description in a WBS dictionary so that the whole team uses the same language.

Worked example

A training project has three deliverables. Course design is estimated at 12,000, delivery at 20,000 and evaluation at 4,000.

  1. Total of the work packages: 12,000 + 20,000 + 4,000 = 36,000

Under the 100 per cent rule, the project budget at that level is 36,000 plus any reserves.

In practice

Project teams draft the WBS in a workshop with the people who will do the work, then use it to build the schedule, the cost estimate and the responsibility chart.

Watch out

  • A WBS is organised by deliverables, not by the order work happens; the schedule handles sequence.
  • Breaking work down too far creates admin without adding control.

Learn it properly

Official sources

Facts last checked on 3 November 2026.

Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.

English