Time and materials

Also called T&M, time-and-materials contract, time and materials pricing

In short

A pricing model in which the client pays for the hours or days actually worked at agreed rates, plus expenses, without a fixed total price.

  • Beginner
  • Concept
  • Checked

In detail

Under time and materials, often written T&M, the client pays for effort rather than for a result. The parties agree rates by grade and how expenses are charged, and the supplier invoices regularly for the time recorded. The final cost depends on how long the work takes.

T&M suits work whose scope cannot be defined well in advance: early diagnosis, research, or support where demand varies. It is quick to set up and lets the client change direction without renegotiating. The risk of overrun sits mainly with the client, so good practice adds a ceiling price or a not-to-exceed figure, regular reporting of hours against budget and the right to stop.

Public procurement rules treat T&M as the least preferred contract type for exactly this reason: the supplier has little incentive to be efficient. Buyers are told to use it only when no other type fits, and to monitor it closely. Many engagements start on T&M for discovery and switch to a fixed fee once the scope is clear.

In practice

A firm agrees day rates and a cap of 60 days for a six-week discovery. Each week it reports days used against the cap, and the client approves any extension in writing before the cap is reached.

Watch out

  • Without a cap and regular reporting, T&M can drift far beyond the original estimate.
  • T&M is not "cheaper" or "dearer" than a fixed fee in itself; it moves the overrun risk to the buyer.

Learn it properly

Official sources

Facts last checked on 3 November 2026.

Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.