The total of all direct costs of a unit or job, namely direct materials, direct labour and direct expenses, before any overhead is added.

  • Intermediate
  • Ratio or metric
  • Checked

In detail

Prime cost is the first building block of a full product cost. It collects every cost that can be traced directly to the unit or job: the materials that go into it, the labour of those who make it and any expenses incurred specifically for it, such as a subcontracted process or a royalty per item.

From prime cost, a cost card adds production overhead to reach full production cost, and then, where needed for pricing, a share of administrative and selling overhead to reach total cost. Prime cost is therefore useful for seeing how much of a product's cost is directly controllable through purchasing and labour efficiency, as opposed to shared overheads.

In hospitality the term is used slightly differently: restaurants often call the combined cost of food, drink and labour their prime cost and track it as a share of sales. Comparing prime cost per unit across batches or sites quickly shows where material waste or labour inefficiency is pushing costs up.

Formula

Prime cost = Direct materials + Direct labour + Direct expenses

Direct materials
materials that become part of the product
Direct labour
wages for time spent making the product
Direct expenses
other costs incurred specifically for the unit or job

Worked example

A batch of 100 printed T-shirts uses blank shirts costing 400, ink costing 60, 5 hours of printing labour at 20 an hour and a design licence fee of 50.

  1. Direct materials: 400 + 60 = 460
  2. Direct labour: 5 × 20 = 100
  3. Prime cost: 460 + 100 + 50 = 610
  4. Per shirt: 610 / 100 = 6.10

The batch has a prime cost of 610, or 6.10 a shirt.

In practice

Job shops quote prices by building up prime cost from materials lists and estimated hours, then adding overhead at a percentage rate and a profit margin.

Watch out

  • Prime cost excludes all overhead, so it understates the full cost of production.
  • The restaurant meaning, food plus labour, is not the same as the costing definition.