Planning fallacy

In short

The tendency to underestimate how long a project will take and how much it will cost, even when similar projects have overrun in the past.

  • Advanced
  • Process
  • Checked

In detail

The planning fallacy is a well-documented habit of human judgement: people forecasting their own projects picture the steps going smoothly and leave too little room for delays, mistakes and surprises. Students underestimate how long essays take, households underestimate renovation bills and governments underestimate the cost of bridges, railways and stadiums. Crucially, people do this even when they know that their own earlier projects ran late.

For investors, the fallacy matters wherever company value depends on a plan being delivered: a new factory, a mine coming into production, a drug trial, a software launch or a merger's promised savings. Overruns delay cash flows and raise costs, and both lower what a project is worth. A business plan that assumes everything goes to schedule is, on the evidence, unlikely to be met in full, and markets often react sharply when a company admits that a flagship project is late or over budget.

The main cure is to take the outside view: look at how long and how costly comparable projects actually were and use that as the baseline. UK government appraisal guidance asks departments to add an explicit allowance for optimism bias to cost and time estimates. Pre-mortems, independent reviews and breaking work into small stages with checkpoints also help.

Worked example

Kestrel Foods says its new plant will cost ₦40bn and open in 18 months. Past plants of this kind in the region ran about 25% over budget and 6 months late.

  1. Adjusted cost: ₦40bn × 1.25 = ₦50bn
  2. Adjusted timing: 18 + 6 = 24 months

An analyst using past overruns would model about ₦50bn and 24 months rather than the plan's figures.

In practice

Analysts add contingencies to company capital spending plans, and project lenders hire independent engineers to test schedules. Public bodies in the UK and elsewhere publish optimism-bias adjustments for different types of project.

Watch out

  • The planning fallacy concerns one's own plans; outsiders judging the same project are often less optimistic.
  • Adding a vague buffer is weaker than basing it on data from similar projects.