Stockertim Dictionary · Accounting
Overhead absorption rate
Also called OAR, predetermined overhead rate, overhead recovery rate
In short
Budgeted overhead divided by budgeted activity, giving the amount of overhead charged to each unit, labour hour or machine hour.
- Intermediate
- Ratio or metric
- Checked
In detail
Overheads cannot be traced to units, so absorption costing charges them through a rate. The rate is set in advance from the budget: estimated overhead for the period divided by estimated activity, measured in units, direct labour hours or machine hours. Each product then absorbs overhead according to how much of that activity it uses.
Using a predetermined rate lets the business cost jobs and price products during the period, without waiting for actual overhead to be known, and avoids unit costs swinging with seasonal activity. The choice of activity base matters: a labour-intensive department suits labour hours, an automated one machine hours. Large organisations set separate rates by department or cost centre after apportioning service costs.
Because the rate is based on estimates, the overhead absorbed rarely equals the overhead actually incurred. The difference, under- or over-absorption, is charged or credited to profit at the period end. Rates are normally reviewed each year when the budget is set, and sooner if activity or spending changes materially.
Formula
Overhead absorption rate = Budgeted overhead / Budgeted activity
- Budgeted overhead
- estimated overhead for the period
- Budgeted activity
- estimated units, labour hours or machine hours
Worked example
A machining department budgets overhead of 360,000 and 24,000 machine hours. A job uses 15 machine hours.
- Rate: 360,000 / 24,000 = 15 per machine hour
- Overhead charged to the job: 15 × 15 = 225
The job absorbs 225 of overhead.
In practice
Engineering and printing firms quote jobs by estimating machine hours and multiplying by the department's overhead rate before adding materials, labour and margin.
Watch out
- A rate based on unrealistic budgeted activity distorts every product cost.
- IAS 2 requires normal capacity, not unusually low actual output, as the base for inventory.
Learn it properly
Official sources
- IAS 2 Inventories · IFRS Foundation
- SFFAS 4: Managerial Cost Accounting Standards and Concepts · Federal Accounting Standards Advisory Board
Facts last checked on 3 November 2026.
Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.