Lessons-learned review

Also called lessons learned, lessons learnt, post-project review, retrospective

In short

A structured meeting at the end of a project or phase in which the team records what went well, what did not and what to do differently next time.

  • Beginner
  • Process
  • Checked

In detail

A lessons-learned review turns experience into knowledge the organisation can reuse. The team, and ideally the sponsor and key stakeholders, look back at the project or phase and ask a few simple questions: what did we plan, what actually happened, why was there a difference, and what should we keep or change next time.

Good reviews are honest and blame-free. The aim is to understand causes, not to find someone to criticise, so a neutral facilitator often helps. Evidence such as schedules, cost reports and issue logs keeps the discussion factual. The output is a short list of specific, actionable lessons, each with someone responsible for passing it on.

The common failure is that lessons are written down and never read. Audit bodies reviewing major programmes have repeatedly found the same mistakes recurring because lessons were filed rather than applied. Organisations that benefit build lessons into templates, checklists and the start-up of new projects.

In practice

Many teams hold short reviews at the end of each stage as well as at closure, and new projects are asked at their first gate which past lessons they have applied.

Watch out

  • A review held months after closure relies on fading memories.
  • Lessons that are not acted on are only observations.