Skip to content

Noch nicht auf Deutsch verfügbar. Alles auf Deutsch ansehen

Stockertim Dictionary · Project management

Earned value

Also called EV, budgeted cost of work performed, BCWP, earned value management, EVM

In short

The budgeted cost of the work actually completed by a given date, used to measure progress in money terms whatever the work really cost.

  • Intermediate
  • Ratio or metric
  • Checked

In detail

Earned value measures progress by asking what the completed work was worth according to the budget. If a work package budgeted at 40,000 is half done, it has earned 20,000, whether the team actually spent 15,000 or 30,000 doing it. Adding the earned value of all packages gives the project's progress in a single currency.

Earned value management compares three figures. Planned value shows what should have been done, earned value what has been done, and actual cost what was spent. The gaps give schedule and cost variances, and the ratios give performance indices that can be used to forecast the final cost and finish date.

The method depends on honest measurement of completion. Many organisations use simple rules, such as zero per cent until a package starts, fifty per cent when it starts and the rest when it finishes, to stop optimistic claims. Large public projects in several countries are required to use earned value management, and the guidance sets out how systems should be built and audited.

Formula

Cost variance = EV - AC

EV
earned value to date
AC
actual cost to date

Worked example

A package budgeted at 40,000 is 50% complete. The team has spent 26,000 on it.

  1. Earned value: 0.50 × 40,000 = 20,000
  2. Cost variance: 20,000 - 26,000 = -6,000

The package is over budget for the work done by 6,000.

In practice

Defence, energy and infrastructure projects report earned value monthly, and auditors check that the baseline, progress claims and actual costs are recorded consistently.

Watch out

  • Earned value measures progress against the plan, not whether the product meets the need.
  • Generous completion estimates make earned value look better than reality.

Learn it properly

Official sources

Facts last checked on 3 November 2026.

Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.

English