Days budget

Also called audit days budget, resource budget, productive days

In short

The number of productive auditor days available in a year after leave, training, holidays and administration, which limits how much can be audited.

  • Advanced
  • Ratio or metric
  • Checked

In detail

An internal auditor employed for a year does not spend every working day on audits. Holidays, public holidays, training, team meetings, administration and sickness all take time. The days budget is what remains for audit work, and it sets a hard limit on the annual plan. Calculating it honestly is the first step in deciding which engagements are feasible.

Functions usually calculate days per person and then add them up across the team, adjusting for vacancies, part-time staff, new joiners who need time to become productive and any co-sourced specialists. Senior staff may have lower audit days because of management duties. A common result is that each full-time auditor provides somewhere around two thirds to three quarters of the year's working days for engagements.

The days budget is compared with the days needed to cover high-risk areas. A shortfall is a resource gap that the chief audit executive reports to the audit committee, along with options such as extra staff, co-sourcing or accepting lower coverage.

Formula

Productive days = working days - leave - public holidays - training - administration

working days
days in the year an employee is contracted to work
leave
annual holiday entitlement
public holidays
bank or public holidays
training
days spent on courses and professional development
administration
meetings, planning and other non-audit time

Worked example

An auditor has 260 working days, 25 days of leave, 8 public holidays, 10 training days and 27 days of administration.

  1. Productive days: 260 - 25 - 8 - 10 - 27 = 190
  2. Team of 6 auditors: 190 × 6 = 1,140

The team can plan about 1,140 days of engagement work for the year.

In practice

Audit managers track actual days against the budget for each engagement, and variances feed future planning.

Watch out

  • A plan built on 100% of working days cannot be delivered.
  • Vacancies reduce the budget immediately.