Skip to content

아직 한국어로 제공되지 않습니다. 한국어로 제공되는 모든 내용 보기

Stockertim Dictionary · Project management

Critical path

Also called critical path method

In short

The longest chain of dependent activities through a project network, which sets the shortest possible project duration and has no float.

  • Intermediate
  • Concept
  • Checked

In detail

The critical path is the sequence of activities that determines how long the project must take. Because each activity on it depends on the one before, and the chain is the longest route through the network, any delay on the critical path delays the whole project by the same amount. Activities off the critical path have some float and can slip a little without moving the end date.

Finding it is arithmetic. Add the durations along each route from start to finish; the route with the largest total is critical. In practice the forward and backward passes do this for every activity at once, and activities with zero total float form the critical path.

The critical path tells managers where to focus. Speeding up a non-critical activity does not shorten the project; shortening a critical one does, until another path becomes the longest. The path can change during the project as activities finish early or late, so it must be recalculated whenever the schedule is updated.

Worked example

A project has two routes. Route 1 is design 5 days, build 10 days and test 4 days. Route 2 is procurement 8 days and installation 6 days, ending at the same point.

  1. Route 1: 5 + 10 + 4 = 19 days
  2. Route 2: 8 + 6 = 14 days
  3. Float on route 2: 19 - 14 = 5 days

Route 1 is the critical path; the project needs at least 19 days.

In practice

Status reports highlight critical-path activities, and schedule reviews ask whether the critical path is realistic and whether near-critical paths could take over.

Watch out

  • The critical path is the longest path, not the most important or most difficult work.
  • Resource limits can create a longer real path than the logic alone shows.

Learn it properly

Official sources

Facts last checked on 3 November 2026.

Education, not advice: the Stockertim Dictionary explains what terms mean. It never recommends buying or selling anything.

English